Since 1977 we’ve been transforming homes in and around Fond du Lac and we’ve grown to a point where we need a new home of our own. Construction is underway as we update and convert the old Kwik Trip on West Scott Street into our new headquarters! Please stop back to see project updates and short videos of this exciting project.

New Home for Wrightway Home Improvements
235 West Scott St
Fond du Lac, WI 54935
MAP

 

2/21/2019 UPDATE

The showroom begins to take shape. Interior framing is complete, wiring is in progress. Once we have a day above 40 degrees, we can insulate and seal up shell and begin finish work.

1/23/2019 UPDATE

Plumbing and HVAC work in progress.

1/12/2019 UPDATE

Jon provides another review of our progress.


12/28/2018 UPDATE

Jon is giving us a quick update on what we’ve been up to and what are plans are for the new building. How exciting!



12/23/2018 UPDATE

There is nothing like getting a new roof for Christmas!



12/16/2018 UPDATE

New roof system is being installed.

 



12/12/2018 UPDATE

New trusses are being set. It’s starting to come together.



12/10/2018 UPDATE

The roof is open! Trusses are coming soon. Hopefully new siding too ūüôā



11/20/2018 UPDATE

We’re working on refining the interior layout, but it feels like we are getting closer on our exterior plans. Here’s a look at the color scheme we’re planning for the exterior.

  • Boral Stone Coated Steel Roofing
  • Boral Stone
  • Seamless Steel Siding
  • Infinity from Marvin Windows

 



11/15/2018 UPDATE

Take a look at our new plans for converting the old Kwik Trip into our new office.

For reference, here’s the existing building –



11/02/2018 UPDATE

We’ve selected our new building! Time to start planning. Here are a few before photos.